ELECTRICITY
2016 List of Current Open Cases and Issues
Electricity
Case No
Description
2
Electric Quality of Service Standards (EQSS), monthly outage reports, outage investigations, and follow-up and electric service restoration issues
3
Pepco's default Standard Offer Service (SOS) for electricity customers who have not chosen an alternative generation supplier and transmission rate deadband filings
4
Mid-Atlantic Distributed Resources Initiative (MADRI) model small generator interconnection procedures
5
Pepco's implementation of Advanced Metering Infrastructure (AMI) including the deployment of smart meters and the development and implementation of a customer education program through the AMI Customer Education Working Group
7
FC 1085
Commission's investigation into a launch of a purchase of receivables (POR) program in the District of Columbia and the implementation of the POR program (Formal Case Closed in CY2016)
9
Washington Gas Energy Services' petition for an investigation into retail electricity supplier access to smart meter data
10
Pepco's application for a certificate authorizing it to issue and sell up to $850,000,000.00 of long-term secured and unsecured debt securities
11
OPC's petition for an investigation to establish a mechanism by which Pepco's management compensation will be adjusted for poor electric distribution system reliability performance in DC
12
Commission's investigation into the business and solicitation practices of Starion Energy in the District
13
Commission's investigation of the policy, economic, legal and technical issues and questions related to establishing a dynamic pricing plan in the District of Columbia. Suspended as of May 13, 2015, pursuant to Commission Order No. 17877
15
Pepco's formal notice of plans to construct four 138 kV underground transmission circuits between Little Falls Parkway in Maryland and Pepco's Van Ness Substation in Northwest, DC
16
Merger of Exelon Corporation, Pepco Holdings, Inc., Potomac Electric Power Company, Exelon Energy Delivery Company, LLC and New Special Purpose Entity, LLC
19
Pepco's formal notice of plans to construct a 230 kV/138 kV/13 kV substation and four 230 kV/138 kV underground transmission circuits on Buzzard Point in Southwest, D.C.
20
Pepco's application for authorization to issue $750,000,000.00 of long-term secured or unsecured debt securities
22
FC 1132
Pepco’s notice of tenants’ rights and options and preliminary election card - Kings Crossing Condominiums (Formal Case Closed in CY2016)
23
Pepco's formal notice of plans to construct two 230 kV underground transmission circuits on Buzzard Point in Southwest, DC
24
Pepco's application for authority to increase existing retail rates and charges for electric distribution service (Formal Case Opened in CY2016)